题目内容 (请给出正确答案)
[主观题]

159Since risk is associated with most projects, the best course of action is to: A.cover a

159 Since risk is associated with most projects, the best course of action is to:

A. cover all project risks by buying appropriate insurance

B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C. avoid projects with clear and present risks

D. eliminate all known risks prior to the execution phase of the project

E. identify various risks and implement actions to mitigate their potential impact

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“159Since risk is associated wi…”相关的问题
第1题
70Which phase of the project life cycle typically has the highest uncertainty and risk ass

70 Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? A. concept

B. development

C. execution

D. conclusion

E. All of the above

点击查看答案
第2题
ass♂we♂can出自哪位哲人之手?

A.苏格拉底

B.比利海灵顿

C.孔子

D.马克思

点击查看答案
第3题
ASS的病因病机有哪些?()

A.遗传因素

B.环境因素

C.病毒感染

D.免疫异常

E.以上都是

点击查看答案
第4题
113Screening of risk events for potential risk is known as _____ . A.problem structuring.

113 Screening of risk events for potential risk is known as _____ .

A. problem structuring.

B. risk identification

C. risk quantification

D. risk modeling

E. risk mitigation

点击查看答案
第5题
97Risks include the following types: A.Business risk B.pure risk C.Insurable risk D.A and

97 Risks include the following types:

A. Business risk

B. pure risk

C. Insurable risk

D. A and B

E. All of the above

点击查看答案
第6题
93The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

93 The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A. buyer's risk

B. consumer's risk

C. producer's risk

D. type I error

E. B and D only

点击查看答案
第7题
4Total Project Risk: A.should not be calculated for small projects B.is the probability of

4 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C

点击查看答案
第8题
84Risk can be divided into two basic types; business risk and pure (or insurable risk). Of

84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

A. liability loss

B. direct property loss

C. profit loss

D. personnel-related loss

E. B and C

点击查看答案
第9题
15Risks include the following types: A.Business risk B.pure risk C.Insurable risk D.A and

15 Risks include the following types:

A. Business risk

B. pure risk

C. Insurable risk

D. A and B

E. All of the above

点击查看答案
第10题
Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.

点击查看答案
第11题
The schedule risk is the _____ .Athe accumulated "expected' durations which maintain proje

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.

点击查看答案