见下表 月份 BCWS BCWP ACWP 六月 34000 34000 33000 七月 18000 16000 20000 八月 58
见下表
月份 BCWS BCWP ACWP
六月 34000 34000 33000
七月 18000 16000 20000
八月 58000 60000 66000
根据上表八月份的成本进度的比较与七月的对比表明方差值$已经__________比率变化已___________()
A.变糟变糟
B.变糟改进
C.改进增加
D.改进变差
E.都不对
见下表
月份 BCWS BCWP ACWP
六月 34000 34000 33000
七月 18000 16000 20000
八月 58000 60000 66000
根据上表八月份的成本进度的比较与七月的对比表明方差值$已经__________比率变化已___________()
A.变糟变糟
B.变糟改进
C.改进增加
D.改进变差
E.都不对
见下图
WBS构成部份 BCWS BCWP ACWP
P 1000 1100 1150
Q 2000 1800 2100
R 1000 1200 1050
S 2000 1900 1800
WBS中P部分的SPI进度执行指数值是()
A.1.10
B.0.90
C.0.956
D.1.15
E.0.869
The difference between the BCWS and the BCWP is referred to as the:
A . Schedule variance
B . Cost variance.
C . Estimate of completion
D . Actual cost of the work performed
E . None of the above
18 The difference between the BCWS and the BCWP is referred to as the:
A. Schedule variance
B Cost variance.
C. Estimate of completion
D. Actual cost of the work performed
E. None of the above
费用偏差的公式为
a. 成本偏差(CV)=已完成工作预算成本(BCWP)-计划工作预算成本(BCWS)
b. 成本偏差(CV)=已完成工作预算成本(BCWP)-完成工作实际成本(ACWP)
c. 成本偏差(CV)=进度偏差(SV)除以计划工作预算成本(BCWS)
d. A和c
a.–$150
b. $150
c. -$50
d. $50
On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A . ¥-100
B . ¥100
C . ¥-150
D . ¥150
E . 85%
52 On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850. Calculate the schedule variance:
A. ($100)
B. $100
C. ($150)
D. $150
E. 85%