164 Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ .
A. Slack for each activity, critical path.
B. Slack for each activity, high risk activities.
C. Manpower shortages, high risk activities.
D. High risk activities, non-critical paths.
E. Manpower availability, contingency plans