117The project charter: A.Expresses upper management commitment to the project. B.Provides

117 The project charter:

A. Expresses upper management commitment to the project.

B. Provides that authority by which the project will be run.

C. Establishes that organizational structure with the project.

D. Specifies overall objectives and timeframe. of the project.

E. All of the above

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“117The project charter: A.Expr…”相关的问题
第1题
143The document authorizing functional areas to charge against the project is the: A.Work

143 The document authorizing functional areas to charge against the project is the:

A. Work authorization form.

B. Scope baseline

C. Project charter

D. Management plan

E. Linear responsibility chart

点击查看答案
第2题
47During the planning phase of a project, you realize that more than one functional depart

47 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

A. Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

B. Let the affected line groups decide among themselves who will perform. the work

C. Ask the executive sponsor to make the decision

D. Allow each line group to perform. part of the task

E. All of the above

点击查看答案
第3题
The document authorizing functional areas to charge against the project is the:A.Work auth

The document authorizing functional areas to charge against the project is the:

A. Work authorization form

B. Scope baseline

C. Project charter

D. Management plan

E .Linear responsibility chart

点击查看答案
第4题
129During the planning phase of a project, you realize that more than one functional depar

129 During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

A. Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

B. Let the affected line groups decide among themselves who will perform. the work

C. Ask the executive sponsor to make the decision

D. Allow each line group to perform. part of the task

E. All of the above

点击查看答案
第5题
80What tool have project managers come to use to identify all of the costs associated with

80 What tool have project managers come to use to identify all of the costs associated with a project.

A. A bill of materials

B. A Gantt chart

C. An arrow diagram network.

D. A work breakdown structure.

E. B and C only

点击查看答案
第6题
68The starting point in the development of a top-down PERT/CPM chart is the _____ . A.Proj

68 The starting point in the development of a top-down PERT/CPM chart is the _____ .

A. Project specification tree.

B. Customer's deliverable list.

C. Customer's milestone dates.

D. Work breakdown structure.

E. Listing of customer team meeting dates

点击查看答案
第7题
198What tool have project managers come to use to identify all of the costs associated wit

198 What tool have project managers come to use to identify all of the costs associated with a project. A. A bill of materials

B. A Gantt chart

C. An arrow diagram network.

D. A work breakdown structure.

E. B and C only

点击查看答案
第8题
61The document authorizing functional areas to charge against the project is the: A.Work a

61 The document authorizing functional areas to charge against the project is the:

A. Work authorization form.

B. Scope baseline

C. Project charter

D. Management plan

E. Linear responsibility chart

点击查看答案
第9题
During the planning phase of a project, you realize that more than one functional departme
nt possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

A.Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

B.Let the affected line groups decide among themselves who will perform. the work

C.Ask the executive sponsor to make the decision

D.Allow each line group to perform. part of the task

E.All of the above

点击查看答案
第10题
150The starting point in the development of a top-down PERT/CPM chart is the _____ . A.Pro

150 The starting point in the development of a top-down PERT/CPM chart is the _____ .

A. Project specification tree.

B. Customer's deliverable list.

C. Customer's milestone dates.

D. Work breakdown structure.

E. Listing of customer team meeting dates

点击查看答案