54 You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most often overlooked?
A. Data item deliverables
B. Customer-furnished equipment and facilities
C. Long-lead procurement items
D. Customer-imposed milestones
E. Other subcontractor interface requirements
Scheduling is the process by which decisions are made concerning:
A.Tasks to be accomplished.
B.Personnel/organization that will be assigned to accomplish the task.
C.Time when the tasks are to be completed.
D.All of the above.
E.A and C only.
22 In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A. Not working directly with the assigned functional employees
B. Employees spend only a short amount of time assigned to the project
C. Not being knowledgeable enough to evaluate employees on technical judgment
D. All of the above
E. A and B only
not be known and the probabilities of their occurring cannot be objectively assigned, is the definition of:
a. Certainty
b. Uncertainty
c. Risk
d. Risk adversity
e. None of the above
104 In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A. Not working directly with the assigned functional employees
B. Employees spend only a short amount of time assigned to the project
C. Not being knowledgeable enough to evaluate employees on technical judgment
D. All of the above
E. A and B only
In a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance review?
A . Not working directly with the assigned functional employees
B . Employees spend only a short amount of time assigned to the project
C . Not being knowledgeable enough to evaluate employees on technical judgment
D . All of the above
E . A and B only
A.Data item deliverables
B.Customer-furnished equipment and facilities
C.Long-lead procurement items
D.Customer-imposed milestones
E.Other subcontractor interface requirements
A Gantt chart is useful in determining:
A.the level of effort for a task
B.when a task starts and stops
C.how tasks are related to each other
D.who is assigned to do a task
E.All of the above.