首页 > 职业资格考试
题目内容 (请给出正确答案)
[主观题]

126A project manager recently rewarded an individual with a promotion that carried with it

126 A project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more responsibility. The project manager appears to be appealing to the employee's _____ need.

A. Monetary

B. Physiological

C. Esteem

D. Self-actualization

E. Team-building

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“126A project manager recently …”相关的问题
第1题
The scope baseline/project charter is prepared by the:AProject managerBProject manager and

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user

点击查看答案
第2题
92The main player in project communication is the A.sponsor B.project manager C.functional

92 The main player in project communication is the

A. sponsor

B. project manager

C. functional manager

D. functional team

E. All of the above

点击查看答案
第3题
93When a project manager is running over the budgeted costs, the project manager can typic

93 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B. Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only

点击查看答案
第4题
The main player in project communication is theAsponsorBproject managerCfunctional manager

The main player in project communication is the

A sponsor

B project manager

C functional manager

D functional team

E All of the above.

点击查看答案
第5题
100Interfacing with the customer after project go-ahead is the responsibility of: A.Projec

100 Interfacing with the customer after project go-ahead is the responsibility of:

A. Project sponsor

B. Project team

C. Project manager

D. Functional manager

E. All of the above are possible, based upon the size and complexity of the project

点击查看答案
第6题
121The quality objectives are approved in the conceptual stage of the project by the: A.Pr

121 The quality objectives are approved in the conceptual stage of the project by the:

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第7题
160The project manager has, as a prime responsibility, to assure proper integration of act

160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. Matrix

B. Classical

C. Expediter

D. Coordinator

E. Pure project

点击查看答案
第8题
112Of the following, who has the ultimate responsibility for meeting project quality objec

112 Of the following, who has the ultimate responsibility for meeting project quality objectives?

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第9题
75A project manager trying to communicate accurately to the team should use: A.the languag

75 A project manager trying to communicate accurately to the team should use:

A. the language of the team members

B. the language of the project manager

C. non-verbal methods

D. written memos

E. All of the above

点击查看答案
第10题
5The scope baseline/project charter is prepared by the: A.Project manager B.Project manage

5 The scope baseline/project charter is prepared by the:

A. Project manager

B. Project manager and project office

C. Project manager, project office and functional team

D. Project manager, project office, functional team and project sponsor

E. Project manager, project sponsor and customer/user

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改