89An element in the WBS was estimated to require 1 month for completion with 1000 hours of

89 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:

A. Higher salaried employees were assigned.

B. Overtime was required.

C. The overhead rate increased.

D. Employee salaries had increased.

E. Any of the above

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“89An element in the WBS was es…”相关的问题
第1题
Using the situation stated in the Special window, which WBS element is behind schedule but
under budget?

A . Element P

B . Element Q

C . Element R

D . Element S

E None of the above.

点击查看答案
第2题
184Using the situation stated in the Special window, which WBS element has a favorable cos

184 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

A. Element P

B. Element Q

C. Element R

D. Element S

E. None of the above

点击查看答案
第3题
element()

A.原因

B.要素

C.保险

D.软件

点击查看答案
第4题
element/'elɪm(ə)nt/()

A.元素

B.要素

C.官僚政治

D.有益

点击查看答案
第5题
create Element和cloneElement有什么区别?
点击查看答案
第6题
102Using the situation stated in the Special window, which WBS element has a favorable cos

102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

A. Element P

B. Element Q

C. Element R

D. Element S

E. None of the above

点击查看答案
第7题
Using the situation stated in the Special window, which WBS element has a favorable cost v
ariance of $150?

A . Element P

B . Element Q

C . Element R

D . Element S

E . None of the above.

点击查看答案
第8题
Element属性是设置显示图像()
点击查看答案
第9题
101Using the situation stated in the Special window, which WBS element is behind schedule

101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

A. Element P

B. Element Q

C. Element R

D. Element S

E. None of the above

点击查看答案
第10题
Which of the following is an element of procurement management:AinspectionBpurchasingCesti

Which of the following is an element of procurement management:

A inspection

B purchasing

C estimating

D expediting