[主观题]

77Since risk is associated with most projects, the best course of action is to: A.cover al

77 Since risk is associated with most projects, the best course of action is to:

A. cover all project risks by buying appropriate insurance

B. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.

C. avoid projects with clear and present risks

D. eliminate all known risks prior to the execution phase of the project

E. identify various risks and implement actions to mitigate their potential impact

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“77Since risk is associated wit…”相关的问题
第1题
关于对学员的定义,以下说法不正确的是()

A.高级学员:总部DGM及以上,门店SGM、Co.SGM

B.中级学员:总部SM-DM、Buyer /E.Sr Buyer,门店SM-DM/ASGM

C.初级学员:总部Asso、Sr.Buyer 、Asst.Buyer,门店SM以下

点击查看答案
第2题
97Risks include the following types: A.Business risk B.pure risk C.Insurable risk D.A and

97 Risks include the following types:

A. Business risk

B. pure risk

C. Insurable risk

D. A and B

E. All of the above

点击查看答案
第3题
Screening of risk events for potential risk is known as _____ .Aproblem structuring.Brisk

Screening of risk events for potential risk is known as _____ .

A problem structuring.

B risk identification

C risk quantification

D risk modeling

E risk mitigation

点击查看答案
第4题
Which of the following is a Principle Risk?A. TPNDB. Risk of ShortageC. War RiskD. All

A. TPND

B. Risk of Shortage

C. War Risk

D. All Risks

点击查看答案
第5题
195Screening of risk events for potential risk is known as _____ . A.problem structuring.

195 Screening of risk events for potential risk is known as _____ .

A. problem structuring.

B. risk identification

C. risk quantification

D. risk modeling

E. risk mitigation

点击查看答案
第6题
93The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

93 The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A. buyer's risk

B. consumer's risk

C. producer's risk

D. type I error

E. B and D only

点击查看答案
第7题
RP 全称为Risk Production()
点击查看答案
第8题
4Total Project Risk: A.should not be calculated for small projects B.is the probability of

4 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C

点击查看答案
第9题
()拯救,解救

A.salvation

B.t risk

C.log

点击查看答案
第10题
Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.