168Statistical cost estimating techniques (based upon history), are called _____ estimates

168 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.

A. Definitive, bottom up.

B. Analogy, top down.

C. Parametric, bottom up.

D. Parametric, top down.

E. Analogy, bottom up

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“168Statistical cost estimating…”相关的问题
第1题
124Warranty cost is an example of an _____ . A.internal failure cost B.appraisal cost C.ex

124 Warranty cost is an example of an _____ .

A. internal failure cost

B. appraisal cost

C. external failure cost

D. customer satisfaction cost

E. All of the above

点击查看答案
第2题
196The Cost Performance Index is computed as: A.budget cost of work performed divided by a

196 The Cost Performance Index is computed as:

A. budget cost of work performed divided by actual cost of work performed

B. budget cost of work performed minus actual cost of work performed

C. budget cost of work performed minus budget cost of work scheduled

D. budget cost of work scheduled divided by budget cost of work performed

E. actual cost of work scheduled divided by budget cost of work performed

点击查看答案
第3题
Warranty cost is an example of an _____ .A.internal failure costB.appraisal costC.external

Warranty cost is an example of an _____ .

A . internal failure cost

B . appraisal cost

C . external failure cost

D . customer satisfaction cost

E . All of the above.

点击查看答案
第4题
Project trade-offs vary betweenA.risk, cost and schedule.B.direct cost, indirect cost, and

Project trade-offs vary between

A . risk, cost and schedule.

B . direct cost, indirect cost, and resource availability

C . quality, schedule and time

D . cost, quality and schedule

E . contract terms, scope and budget

点击查看答案
第5题
32Cost of quality includes: A.Appraisal cost B.detection cost C.prevention cost D.maintena

32 Cost of quality includes:

A. Appraisal cost

B. detection cost

C. prevention cost

D. maintenance cost

E. A, B, and C only

点击查看答案
第6题
12What is the relative priority of project Cost, Schedule and Quality? A.1)Cost - 2)Schedu

12 What is the relative priority of project Cost, Schedule and Quality?

A. 1)Cost - 2)Schedule - 3)Quality

B. 1)Quality - 2)Schedule - 3)Cost

C. 1)Quality - 2)Cost - 3)Schedule

D. 1)Schedule - 2)Quality - 3)Cost

E. All are of equal priority

点击查看答案
第7题
17Using the cumulative cost curve in the special window, height B represents A.actual cost

17 Using the cumulative cost curve in the special window, height B represents

A. actual cost to date

B. total budgeted costs for the project

C. planned cost for month 6

D. cost variance

E. earned value

点击查看答案
第8题
187A budget estimate should give the manager cost data accurate to within: A.-5 to +10 per

187 A budget estimate should give the manager cost data accurate to within:

A. -5 to +10 percent of actual cost

B. -25 to +75 percent of actual cost

C. -30 to +75 percent of actual cost

D. -10 to +25 percent of actual cost

E. None of the above

点击查看答案
第9题
Marginal cost can be derived given total cost at all levels of production.()
点击查看答案
第10题
Depreciation is the systematic and rational allocation of the cost of a depreciable as
点击查看答案