首页 > 职业资格考试
题目内容 (请给出正确答案)
[主观题]

Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“Total project risk can be defi…”相关的问题
第1题
Total Project Risk:Ashould not be calculated for small projectsBis the probability of each

Total Project Risk:

A should not be calculated for small projects

B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D A and B

E A and C

点击查看答案
第2题
4Total Project Risk: A.should not be calculated for small projects B.is the probability of

4 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C

点击查看答案
第3题
Risk event probability is defined as:Athe total number of possible events divided into the

Risk event probability is defined as:

A the total number of possible events divided into the expectations or frequency of the risk event

B the number of times the risk event may occur

C the fraction of the total project tasks which may be affected by the risk event

D the total number of possible events divided into the consequences of the risk event.

E A and B

点击查看答案
第4题
122Total Project Risk: A.should not be calculated for small projects B.is the probability

122 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C

点击查看答案
第5题
26Risk event probability is defined as: A.the total number of possible events divided into

26 Risk event probability is defined as:

A. the total number of possible events divided into the expectations or frequency of the risk event

B. the number of times the risk event may occur

C. the fraction of the total project tasks which may be affected by the risk event

D. the total number of possible events divided into the consequences of the risk event.

E. A and B

点击查看答案
第6题
97Total project risk can be defined as: A.the sum of the probabilities of project risks ev

97 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events

点击查看答案
第7题
15Total project risk can be defined as: A.the sum of the probabilities of project risks ev

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events

点击查看答案
第8题
144Risk event probability is defined as: A.the total number of possible events divided int

144 Risk event probability is defined as:

A. the total number of possible events divided into the expectations or frequency of the risk event

B. the number of times the risk event may occur

C. the fraction of the total project tasks which may be affected by the risk event

D. the total number of possible events divided into the consequences of the risk event.

E. A and B

点击查看答案
第9题
It is useful to conduct project risk assessment according to the project'sAcharterBstateme

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget

点击查看答案
第10题
125In Project Risk Management, Risk Response may include actions to: A.reduce the probabil

125 In Project Risk Management, Risk Response may include actions to:

A. reduce the probability of risk events

B. change the scope, budget, schedule or quality specifications of the project

C. reduce the consequences or severity of impacts of a potential risk event

D. A and C

E. All of the above

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改