86 The contractual statement of work (CSOW)
A. Must be the same as the proposal statement of work
B. Does not identify reporting requirements
C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D. Identifies the contractor's organizational structure for the project
E. All of the above
_____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form. the basis of a contract.
A Request for proposal
B Invitation to bid
C Request for quotation
D Intention for bid
E None of the above.
The contractual statement of work (CSOW)
A.Must be the same as the proposal statement of work
B.Does not identify reporting requirements
C.Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D.Identifies the contractor's organizational structure for the project
E.All of the above
A legally binding document offered unilaterally is a _____ .
A purchase order
B scope of work description
C contract stipulation
D level of effort proposal
E request for proposal
168 The contractual statement of work (CSOW)
A. Must be the same as the proposal statement of work
B. Does not identify reporting requirements
C. Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D. Identifies the contractor's organizational structure for the project
E. All of the above
13 A legally binding document offered unilaterally is a _____ .
A. purchase order
B scope of work description
C. contract stipulation
D. level of effort proposal
E. request for proposal