144Free float is the amount of time that an activity may be delayed with out affecting the
144 Free float is the amount of time that an activity may be delayed with out affecting the _____.
A. Early start of the succeeding activities.
B. Late start of the succeeding activities.
C. Project finish.
D. Cost of the project.
E. None of the above