178Assigning resources in an attempt to find the shortest project schedule consistent with
178 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling
D. Quantification.
E. None of above.