During project execution, a line manager informs you that he will not have sufficient reso

urces available next month to support your and two other projects. The best way to handle this problem would be to:

A.Ask the line manager to make the decision.

B.Ask the line manager to work with senior management to prioritize the work.

C.Ask your sponsor to meet with the line manager.

D.Ask the line manager to set up a meeting with you and the other project managers to work out the problem yourselves.

E.Prepare a purchase order to outsource the work.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“During project execution, a li…”相关的问题
第1题
161Project alternatives are examined during the _____ phase of the project A.conceptual B.

161 Project alternatives are examined during the _____ phase of the project

A. conceptual

B. finish

C. development

D. implementation

E. A and C

点击查看答案
第2题
6Typically, during which phase in a project life cycle are most of the project expenses in

6 Typically, during which phase in a project life cycle are most of the project expenses incurred. A. Concept phase

B Development of design phase

C. Execution phase.

D. Termination phase.

E. None of the above

点击查看答案
第3题
79Project alternatives are examined during the _____ phase of the project A.conceptual B.f

79 Project alternatives are examined during the _____ phase of the project

A. conceptual

B. finish

C. development

D. implementation

E. A and C

点击查看答案
第4题
During which phase of the project life cycle is the amount at stake lowest?AconceptBdevelo

During which phase of the project life cycle is the amount at stake lowest?

A concept

B development

C execution

D conclusion

E C and D

点击查看答案
第5题
10The project manager must be concerned with building a closely knit team. During the proj

10 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with: A. Proposed salary increases if the project is successful

B. Bonuses for early completion date

C. A promise of future assignments

D. Well-defined project objectives

E. Linear responsibility charts

点击查看答案
第6题
Project alternatives are examined during the _____ phase of the projectA.conceptualB.finis

Project alternatives are examined during the _____ phase of the project

A . conceptual

B . finish

C . development

D . implementation

E . A and C

点击查看答案
第7题
164Perhaps the biggest problem facing the project manager during integration activities wi

164 Perhaps the biggest problem facing the project manager during integration activities within a matrix structure is:

A. Coping with employees who report to multiple bosses

B. Too much sponsorship involvement

C. Unclear functional understanding of the technical requirements

D. Escalating project costs

E. All of the above

点击查看答案
第8题
97The following reports are normally developed during the project closure phase? A.Communi

97 The following reports are normally developed during the project closure phase?

A. Communications Management Plan and Lessons Learned

B. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

C. Records Archive, Closure Report, & Specifications Document

D. Communications Management Plan and Closure report

E. None of the above

点击查看答案
第9题
Typically, during which phase in a project life cycle are most of the project expenses inc
urred.

A . Concept phase

B . Development of design phase

C . Execution phase.

D . Termination phase.

E . None of the above

点击查看答案
第10题
Risk management allows the project manager and the project team to:Aeliminate most risks d

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only