All of the following are categories of a milestone in a schedule except:
A.End date.
B.Contract dates.
C.Key events scheduled.
D.Imposed dates.
E.Task duration.
A.Most of all
B.Remember that
C.A key feature
D.For instance
Management plans include all of the following except:
A.Organization of project.
B.Job descriptions.
C.Policies and procedures.
D.Linear responsibility charts.
E.Scope baseline.
A contract is legally binding and must comprise all but one of the following:
A legal capacity
B mutual assent
C approved negotiations
D consideration
E legality
Quality management deals with all of the following except:
A . conformance to requirements/specifications
B . satisfying the needs of the customer
C . making products more desirable and luxurious
D . A and C.
E . B and C
ecipe book.
A、providing
B、provided
C、to provide
A Project Status Report would include all of the following except:
A Cost and schedule reports
B Changes to scope. cost or schedule
C Narrative explanation of variances
D Personnel problems on the project
E Upcoming activities
A.Fresh water
B.Forests in the northwestern United States
C.The advice of economists
D.All the above
E.None of the above
Which of the following is not a cost of non-conformance?
A . maintenance and calibration
B . warranty repairs
C . scrap
D . rework
E . All of the above.
90 Management plans include all of the following except:
A. Organization of project.
B. Job descriptions.
C. Policies and procedures.
D. Linear responsibility charts.
E. Scope baseline.
Which of the following areas are addressed in risk identification:
A environmental
B technical
C legal
D All of the above.
E A and B only