130Standard deviation of project completion is _____ . A.a relationship of the uncertainty
130 Standard deviation of project completion is _____ .
A. a relationship of the uncertainty of critical path activities.
B. an indicator of project end date target confidence
C. a function of critical path, leveling and project costs.
D. A and B
E. All of the above