Using the figure in the Special window, The Critical path is _____ weeks.A.21B.22C.23D.24E
Using the figure in the Special window, The Critical path is _____ weeks.
A . 21
B . 22
C . 23
D . 24
E . 25
Using the figure in the Special window, The Critical path is _____ weeks.
A . 21
B . 22
C . 23
D . 24
E . 25
120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.
A. 2
B. 3
C. 4
D. 5
E. 7
Using the figure in the Special Window, what is the probability of success for Project B?
A 0.3
B 0.2
C 0.35
D 0.15
E 0.12
Using the figure in the Special window, The critical path is:
A . A-B-G
B . C-G
C . C-D
D . E-F
E . A-B-G and C-D
110 Using the figure in the Special window, The critical path is:
A. A-B-G
B. C-G
C. C-D
D. E-F
E. A-B-G and C-D
A . 0
B . 1
C . 2
D . 3
E . 4
114 Using the figure in the Special window, The Critical path is _____ weeks.
A. 21
B. 22
C. 23
D. 24
E. 25
A . 2, 10
B . 4, 12
C . 6, 14
D . 7, 15
E . 9, 17
A . 11, 13
B . 12, 14
C . 13, 15
D . 14, 16
E . 15, 17
111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A. 0
B. 1
C. 2
D. 3
E. 4