首页 > 职业资格考试
题目内容 (请给出正确答案)
[主观题]

182Pure Risk differs from Business Risks because Pure Risk's _____ . A.include chances of

182 Pure Risk differs from Business Risks because Pure Risk's _____ .

A. include chances of both profit or loss associated with the business.

B. include chances of loss and no chances for profit associated with the business.

C. must incur personal loss with business liability.

D. must incur business liability associated with loss of pure profit.

E. B and C

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“182Pure Risk differs from Busi…”相关的问题
第1题
Pure Risk differs from Business Risks because Pure Risk's _____ .Ainclude chances of both

Pure Risk differs from Business Risks because Pure Risk's _____ .

A include chances of both profit or loss associated with the business.

B include chances of loss and no chances for profit associated with the business.

C must incur personal loss with business liability.

D must incur business liability associated with loss of pure profit.

E B and C

点击查看答案
第2题
100Pure Risk differs from Business Risks because Pure Risk's _____ . A.include chances of

100 Pure Risk differs from Business Risks because Pure Risk's _____ .

A. include chances of both profit or loss associated with the business.

B. include chances of loss and no chances for profit associated with the business.

C. must incur personal loss with business liability.

D. must incur business liability associated with loss of pure profit.

E. B and C

点击查看答案
第3题
The turning point differs from the inciting incident in that it is associated with som
点击查看答案
第4题
Japanese differs ______ Chinese in many respects.

A.on

B.at

C.in

D.from

点击查看答案
第5题
From the text we know that_______

A、Win 2000 retains few features of the NT 4.0

B、Win 2000 differs a lot from the NT 4.0

C、Win 2000 is the same as the Windows version NT 5.0

D、NT 4.0 and Windows 2000 have almost the same characteristics

点击查看答案
第6题
113Screening of risk events for potential risk is known as _____ . A.problem structuring.

113 Screening of risk events for potential risk is known as _____ .

A. problem structuring.

B. risk identification

C. risk quantification

D. risk modeling

E. risk mitigation

点击查看答案
第7题
84Risk can be divided into two basic types; business risk and pure (or insurable risk). Of

84 Risk can be divided into two basic types; business risk and pure (or insurable risk). Of the following, which one(s) fall(s) under business risk?

A. liability loss

B. direct property loss

C. profit loss

D. personnel-related loss

E. B and C

点击查看答案
第8题
4Total Project Risk: A.should not be calculated for small projects B.is the probability of

4 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C

点击查看答案
第9题
15Risks include the following types: A.Business risk B.pure risk C.Insurable risk D.A and

15 Risks include the following types:

A. Business risk

B. pure risk

C. Insurable risk

D. A and B

E. All of the above

点击查看答案
第10题
Total project risk can be defined as:Athe sum of the probabilities of project risks events

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.

点击查看答案
第11题
The schedule risk is the _____ .Athe accumulated "expected' durations which maintain proje

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改