首页 > 职业资格考试
题目内容 (请给出正确答案)
[主观题]

The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost co

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“The Work Breakdown Structure (…”相关的问题
第1题
13The work breakdown structure, the work packages, and the company's accounting system are

13 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:

A. Code of accounts.

B. Overhead rates.

C. Budgeting system.

D. Capital budgeting process.

E. All of the above.

点击查看答案
第2题
111It is useful to conduct project risk assessment according to the project's A.charter B.

111 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget

点击查看答案
第3题
131The work breakdown structure, the work packages, and the company's accounting system ar

131 The work breakdown structure, the work packages, and the company's accounting system are tied together through the:

A. Code of accounts.

B. Overhead rates.

C. Budgeting system.

D. Capital budgeting process.

E. All of the above

点击查看答案
第4题
193It is useful to conduct project risk assessment according to the project's A.charter B.

193 It is useful to conduct project risk assessment according to the project's

A. charter

B. statement of work

C. Work Breakdown structure

D. network

E. budget

点击查看答案
第5题
It is useful to conduct project risk assessment according to the project'sAcharterBstateme

It is useful to conduct project risk assessment according to the project's

A charter

B statement of work

C Work Breakdown structure

D network

E budget

点击查看答案
第6题
The work breakdown structure, the work packages, and the company's accounting system are t
ied together through the:

A . Code of accounts.

B . Overhead rates.

C . Budgeting system.

D . Capital budgeting process.

E . All of the above.

点击查看答案
第7题
68The starting point in the development of a top-down PERT/CPM chart is the _____ . A.Proj

68 The starting point in the development of a top-down PERT/CPM chart is the _____ .

A. Project specification tree.

B. Customer's deliverable list.

C. Customer's milestone dates.

D. Work breakdown structure.

E. Listing of customer team meeting dates

点击查看答案
第8题
45A clear definition of the user's needs serves as the direct basis for the: A.Work breakd

45 A clear definition of the user's needs serves as the direct basis for the:

A. Work breakdown structure.

B. Functional requirements.

C. Project cost estimate.

D. Selection of personnel.

E. Termination decision.

点击查看答案
第9题
150The starting point in the development of a top-down PERT/CPM chart is the _____ . A.Pro

150 The starting point in the development of a top-down PERT/CPM chart is the _____ .

A. Project specification tree.

B. Customer's deliverable list.

C. Customer's milestone dates.

D. Work breakdown structure.

E. Listing of customer team meeting dates

点击查看答案
第10题
A Work Breakdown Structure:A.assures all work is identifiedB.subdivides the project into m

A Work Breakdown Structure:

A.assures all work is identified

B.subdivides the project into manageable segments

C.provides the project sponsor with a time-phase task summary

D.both A and B

E.All of the above.

点击查看答案