181A project manager who, in a deference of opinion with the project controls engineer on

181 A project manager who, in a deference of opinion with the project controls engineer on how costs are to be reported, dictates the format of the cost report may be said to have a conflict management style. A. Withdrawing

B. Forcing

C. Confrontational

D. Authoritarian

E. Combative

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“181A project manager who, in a…”相关的问题
第1题
5The scope baseline/project charter is prepared by the: A.Project manager B.Project manage

5 The scope baseline/project charter is prepared by the:

A. Project manager

B. Project manager and project office

C. Project manager, project office and functional team

D. Project manager, project office, functional team and project sponsor

E. Project manager, project sponsor and customer/user

点击查看答案
第2题
Of the following, who has the ultimate responsibility for meeting project quality objectiv
es?

A . Project Engineer

B . Project Manager

C . Functional Manager

D . Quality Assurance Manager

E . Project Owner

点击查看答案
第3题
3The quality objectives are approved in the conceptual stage of the project by the: A.Proj

3 The quality objectives are approved in the conceptual stage of the project by the:

A. Project Engineer

B. Project Manager

C. Functional Manager

D. Quality Assurance Manager

E. Project Owner

点击查看答案
第4题
The way a project manager sends and receives information depends upon:AHow others relate t

The way a project manager sends and receives information depends upon:

A How others relate to the project manager

B The project manager's level in the organizational hierarchy

C the size and nature of the project

D the project manager's salary and age

E the number of projects going on at one time in the company

点击查看答案
第5题
92The main player in project communication is the A.sponsor B.project manager C.functional

92 The main player in project communication is the

A. sponsor

B. project manager

C. functional manager

D. functional team

E. All of the above

点击查看答案
第6题
The scope baseline/project charter is prepared by the:AProject managerBProject manager and

The scope baseline/project charter is prepared by the:

AProject manager

BProject manager and project office

CProject manager, project office and functional team

DProject manager, project office, functional team and project sponsor

EProject manager, project sponsor and customer/user

点击查看答案
第7题
93When a project manager is running over the budgeted costs, the project manager can typic

93 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B. Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only

点击查看答案
第8题
100Interfacing with the customer after project go-ahead is the responsibility of: A.Projec

100 Interfacing with the customer after project go-ahead is the responsibility of:

A. Project sponsor

B. Project team

C. Project manager

D. Functional manager

E. All of the above are possible, based upon the size and complexity of the project

点击查看答案
第9题
11When a project manager is running over the budgeted costs, the project manager can typic

11 When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget.

A. Reduce features and/or functionality

B Increase risk.

C. Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)

D. All of the above.

E. A and B only

点击查看答案
第10题
160The project manager has, as a prime responsibility, to assure proper integration of act

160 The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work? A. Matrix

B. Classical

C. Expediter

D. Coordinator

E. Pure project

点击查看答案
第11题
75A project manager trying to communicate accurately to the team should use: A.the languag

75 A project manager trying to communicate accurately to the team should use:

A. the language of the team members

B. the language of the project manager

C. non-verbal methods

D. written memos

E. All of the above