41The scope of a project can be expected to change if: A.The project manager must provide
41 The scope of a project can be expected to change if:
A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs
C. The project manager is assigned after the project is defined, and the cost and schedule are approved
D. A clear objective is not provided
E. All of the above are possible based upon the situation