The critical path in a schedule network is the path that:A.Takes the longest time to compl
The critical path in a schedule network is the path that:
A.Takes the longest time to complete
B.Must be done before any other tasks
C.Allows some flexibility in scheduling a start time.
D.Is not affected by schedule slippage
E.All of the above.