The critical path in a schedule network is the path that:A.Takes the longest time to compl

The critical path in a schedule network is the path that:

A.Takes the longest time to complete

B.Must be done before any other tasks

C.Allows some flexibility in scheduling a start time.

D.Is not affected by schedule slippage

E.All of the above.

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“The critical path in a schedul…”相关的问题
第1题
Using the figure in the Special window, The Critical path is _____ weeks.A.21B.22C.23D.24E

Using the figure in the Special window, The Critical path is _____ weeks.

A . 21

B . 22

C . 23

D . 24

E . 25

点击查看答案
第2题
A project element which lies between two events is called:A.An activity.B.A critical path

A project element which lies between two events is called:

A.An activity.

B.A critical path method.

C.A slack milestone.

D.A timing slot.

E.A calendar completion point.

点击查看答案
第3题
Using the figure in the Special window, The critical path is:A.A-B-GB.C-GC.C-DD.E-FE.A-B-G

Using the figure in the Special window, The critical path is:

A . A-B-G

B . C-G

C . C-D

D . E-F

E . A-B-G and C-D

点击查看答案
第4题
The critical path in a network is the path that:A.Has the greatest degree of risk.B.Will e

The critical path in a network is the path that:

A.Has the greatest degree of risk.

B.Will elongate the project if the activities on this path take longer than anticipated.

C.Must be completed before all other paths.

D.All of the above.

E.A and B only.

点击查看答案
第5题
Which of the following impacts the critical path?A.Changing the task duration.B.Reduce the

Which of the following impacts the critical path?

A.Changing the task duration.

B.Reduce the free float of an activity.

C.Executing a backward pass

D.A or B

E.None of the above.

点击查看答案
第6题
110Using the figure in the Special window, The critical path is: A.A-B-G B.C-G C.C-D D.E-F

110 Using the figure in the Special window, The critical path is:

A. A-B-G

B. C-G

C. C-D

D. E-F

E. A-B-G and C-D

点击查看答案
第7题
63The critical path in a schedule network is the path that: A.Takes the longest time to co

63 The critical path in a schedule network is the path that:

A. Takes the longest time to complete

B. Must be done before any other tasks

C. Allows some flexibility in scheduling a start time.

D. Is not affected by schedule slippage

E. All of the above

点击查看答案
第8题
64The critical path in a network is the path that: A.Has the greatest degree of risk. B.Wi

64 The critical path in a network is the path that:

A. Has the greatest degree of risk.

B. Will elongate the project if the activities on this path take longer than anticipated.

C. Must be completed before all other paths.

D. All of the above.

E. A and B only

点击查看答案
第9题
The schedule risk is the _____ .Athe accumulated "expected' durations which maintain proje

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.