A project manager believes that modifying the scope of the project may provide added value
A.Change the scope baseline
B.Prepare a variance report
C.Call a meeting of the configuration control board
D.Change the project's objectives
E.Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline