61Cost and schedule data are usually integrated because: A.optimized project cash flow can

61 Cost and schedule data are usually integrated because:

A. optimized project cash flow can affect financial requirements

B. they provide MIS with an integrated system to produce reports

C. they control escalation allowances

D. they account for omissions in the definitive estimate

E. they predict future performance

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“61Cost and schedule data are u…”相关的问题
第1题
12What is the relative priority of project Cost, Schedule and Quality? A.1)Cost - 2)Schedu

12 What is the relative priority of project Cost, Schedule and Quality?

A. 1)Cost - 2)Schedule - 3)Quality

B. 1)Quality - 2)Schedule - 3)Cost

C. 1)Quality - 2)Cost - 3)Schedule

D. 1)Schedule - 2)Quality - 3)Cost

E. All are of equal priority

点击查看答案
第2题
What is the relative priority of project Cost, Schedule and Quality?A.1)Cost - 2)Schedule

What is the relative priority of project Cost, Schedule and Quality?

A . 1)Cost - 2)Schedule - 3)Quality

B . 1)Quality - 2)Schedule - 3)Cost

C . 1)Quality - 2)Cost - 3)Schedule

D . 1)Schedule - 2)Quality - 3)Cost

E . All are of equal priority

点击查看答案
第3题
Public()

A.unknown

B.schedule

C.recovery

D.transport

点击查看答案
第4题
The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost co

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.

点击查看答案
第5题
日程这个单词怎么拼()

A.scedule

B.schedale

C.schedule

点击查看答案
第6题
The critical path in a schedule network is the path that:A.Takes the longest time to compl

The critical path in a schedule network is the path that:

A.Takes the longest time to complete

B.Must be done before any other tasks

C.Allows some flexibility in scheduling a start time.

D.Is not affected by schedule slippage

E.All of the above.

点击查看答案
第7题
Though an operating system can schedule the execution of jobs, it does not manage the
点击查看答案
第8题
125Which of the following does not contribute to increased Schedule Risk? A.labor shortage

125 Which of the following does not contribute to increased Schedule Risk?

A. labor shortage

B. contractor claims

C. lack of access

D. sponsor scope changes

E. all may increase schedule risk

点击查看答案
第9题
Can you show me the schedule? ().A、 Don’t worry. I can help you with thatB、 You won’t mi

Can you show me the schedule? ().

A、 Don’t worry. I can help you with that

B、 You won’t miss the plane

C、 Sure, a tight schedule as usual

点击查看答案
第10题
2The Work Breakdown Structure (WBS) is the basis for communicating: A.Project scope, cost

2 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments