Resource leveling will often affect the project by making it:A.Shorter.B.LongerC.More resp
Resource leveling will often affect the project by making it:
A.Shorter.
B.Longer
C.More responsive to customer needs.
D.A and C
E.B and C.
Resource leveling will often affect the project by making it:
A.Shorter.
B.Longer
C.More responsive to customer needs.
D.A and C
E.B and C.
53 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
122 Resource leveling will often affect the project by making it:
A. Shorter.
B. Longer
C. More responsive to customer needs.
D. A and C
E. B and C
Resource leveling _____.
A.Allocates resources to activities to find shortest schedule within fixed resource limits.
B.Smoothes out resource requirements by rescheduling activities within their float time.
C.Smooths out resource requirements by substituting activities with unassigned resources.
D.Attempts to reduce resource requirements within a constraint on project duration
E.B or D
171 Resource leveling _____.
A. Allocates resources to activities to find shortest schedule within fixed resource limits.
B. Smoothes out resource requirements by rescheduling activities within their float time.
C. Smooths out resource requirements by substituting activities with unassigned resources.
D. Attempts to reduce resource requirements within a constraint on project duration
E. B or D
40 Resource leveling will often affect the project by making it:
A. Shorter.
B. Longer
C. More responsive to customer needs.
D. A and C
E. B and C
60 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling
D. Quantification.
E. None of above.
178 Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A. Allocation.
B. Partitioning
C. Leveling
D. Quantification.
E. None of above.
130 Standard deviation of project completion is _____ .
A. a relationship of the uncertainty of critical path activities.
B. an indicator of project end date target confidence
C. a function of critical path, leveling and project costs.
D. A and B
E. All of the above
Standard deviation of project completion is _____ .
A a relationship of the uncertainty of critical path activities.
B an indicator of project end date target confidence
C a function of critical path, leveling and project costs.
D A and B
E All of the above.